Project Update
In December 2025 Council approved to proceed to the detailed design phase, reflecting the changes outlined in the Council Committee Report.
For further information and the design please see the Council Committee Report in the document library on this page. For minutes of the meeting see the Council Meeting page.
In 2026 Council will progress the detailed design, provide updates to the community, apply for grant funding to deliver the works and proceed to procurement for the construction phase, once funded.
Key Information
We invite you to give feedback about the proposed design for Denham Street and Edward Street (intersection).
Concerns of residents about this location:
- A combination of higher traffic volume and speeds compared to surrounding areas
- Higher fatality and serious injury probability risk (FSI) compared to surrounding areas
- Poor visibility of pedestrians potentially crossing using the median treatment are present
- Poor visibility for the right-hand turn into and turn out of Edward Street
Proposed design and traffic calming:
- New continuous footpath on Edward Street (north) and new reinforced concrete footpath
- Existing pedestrian island, kerb islands and kerb ramps removed
- New separated bicycle lane line marking for the intersection
- New garden beds and street trees
- Two additional street parking spaces.