Project Update: Separable Portion 2 (SP2) Civil Works

This update is to inform of the recent Council motion passed to cease the planned Separable Portion 2 (SP2) civil upgrade works at the intersection of Bronte Rd, Carrington Rd & Victoria St.

You can view a map of the SP1 and SP2 work scope areas below.

Locations within SP2 disturbed by the preliminary electrical works trenching will be reinstated to match surrounding existing materiality, without carrying out further upgrades. The geometric layout of the intersection will remain unchanged as from existing conditions.

The decision to remove the SP2 portion of works from the project scope was made following ongoing discussions with local residents and businesses on the project’s impacts, construction timeframe and concerns over removal of the slip lane from Bronte Road to Carrington Road.

The infrastructure installed to date in the process of undergrounding the power within SP2 will be able to be utilised in future for easy connectivity to power for any Transport for NSW or Council roads enhancement projects.

The main civil works, including landscaping, are on track to be completed in November 2025. Some civil works cannot be completed until the Ausgrid poles in the SP1 area have been removed, with every effort being made to have this done before the end of 2025.


You are welcome to provide feedback on the decision made to reduce the scope of the project and can submit feedback below.

November 2025: Landscaping underway

The streets of Charing Cross are getting greener! Landscaping works are underway at Charing Cross with a mix of Australian natives bringing life and colour around kerbs and footpaths.

Civil works and electrical works are on track to be completed in November 2025, with some further pole removal works subjected to Ausgrid scheduling. Notification will be provided in advance of upcoming works as the project enters its final stages.

Review of Environmental Factors (REF)

The REF is a detailed, peer-reviewed report that looks at all the factors impacted by a project, including socio-economic, traffic, heritage, sustainability and others.

Council received public feedback on the REF (including the detailed design plans) between 2 - 29 November 2023.

We are currently consolidating all the feedback collected during this period to provide to our external consultants.

To view all REF peer review documents please refer to the Important Documents section of this page.

Consultation round 1

In March 2020, we consulted residents and local business owners in Charing Cross to make sure the scope of the project aligned with the community's needs. This feedback was used to inform the detailed concept design for the streetscape upgrade.

Consultation round 2

From 21 April - 19 May 2021 we went back to the community with draft concept designs for the streetscape upgrade.

The objectives were to:

  • Provide the community with clear information so their feedback on the proposed concept is specific and applicable
  • Identify and work with stakeholders to refine issues and key elements of the project

Overall, we received 433 submissions from the community, including 200 survey responses, 126 posts on the ideas board and 107 pieces of face-to-face feedback. All feedback was compiled in a Consultation Summary Report.


How feedback was collected:

  • An online survey (see below)
  • Ideas board (see below)
  • Postal
  • An online community info session held on 6 May 2021
  • Two Have Your Say days held to collect face to face feedback
    • 30 April 2021 - 7:30-10:30am, opposite the Legions Club
    • 1 May 2021 - 7:30-10:30am, opposite the Legions Club