Project Background

Curlewis Street has been selected by TfNSW and support by Waverley Council as a priority route for a bike path. This is a key route between Woollahra and Waverley and this project will better connect the key destination of Bondi Beach and Rose Bay. The upgrade will also improve accessibility to Bondi Beach via Bondi Road and Curlewis Street and connect to Woollahra's Rose Bay ferry.

Curlewis Street is an important community hub which marks the entrance to Bondi Beach and the Waverley area. This project aims to make the area safer for all road users, promote active transport and create a more inviting and vibrant space for the community to enjoy.

Key Features of the Upgrade

  • Establishing a new separated two-way bike path from Campbell Pde to Wellington St
  • Creating shared paths for pedestrians and bike riders at the western end of Curlewis St (from Old South Head Rd to Wellington St). These shared paths have been proposed based on the constraints and uses of the road environment.
  • Converting existing pedestrian crossings at Gould St and Wellington St into raised pedestrian crossings with a designated lane for bikes to cross
  • Creating an improved outdoor dining environment
  • Establishing new plantings and increasing the tree canopy by planting approximately 60 new trees
  • Installing new paving and signage
  • Replacing existing light poles with multifunction poles
  • Improving drainage and stormwater quality
  • Installing six new EV charging stations

Proudly Funded by the NSW Government in association with Waverley Council.


Project Update: May 2026

Intersection Upgrade Works - Glenayr Avenue and Curlewis Street

Project Update

Curlewis Street Streetscape Upgrade works are progressing into the final stage of construction, with several key milestones achieved in recent months. These include the completion of new footpaths, kerb and gutter, and cycleway works between Wellington Street and Glenayr Avenue.

Recent works have also included the installation of soil and turf with verge areas and completion of asphalting along the gutter lip between Wellington Street and Glenayr Avenue. As a result, on-site street parking has now been restored along the northern side of Curlewis Street within this section. Progress has also been made on the installation of the new traffic control signals (TCS) posts with challenging underground conditions requiring additional construction works.

We’re entering the final stages of construction, with approximately 8 weeks of work remaining, commencing Wednesday, 6 May 2026 (weather permitting).

To complete the Curlewis St Streetscape Upgrade efficiently, works will be delivered in a staged approach across each corner of the intersection between Curlewis Street and Glenayr Avenue, followed by final paving and traffic signal installation.


Upcoming Construction Activity

  • Week 1: Civil works – South Western corner
  • Weeks 2–3: Civil works – North Western corner
  • Week 4: Civil works – South Eastern corner
  • Week 5: Civil works – North Eastern corner
  • Week 6: Paving works across all corners
  • Weeks 7–8: Traffic Control Signal (TCS) pole installation and commissioning.

What to Expect

During these stages, you may notice the following:

  • Temporary changes to pedestrian and traffic access around the intersection
  • Construction vehicles and equipment in operation
  • Periods of increased noise during standard work hours.

We’ll continue to keep the community informed about the progress of these essential works and provide updates if there are any changes to the schedule.


Work Hours

Works are scheduled between 7:00AM and 5:00PM Monday to Friday. Some night works will be expected at a later stage.

A separate notification with further details will be provided in advance of any planning night works.


Curlewis St Streetscape Upgrade Completed Works


REF Documentation and Feedback Form

Consultation: First round

From 18 May - 15 June 2022 we collected feedback on a draft concept design for the upgrade of Curlewis Street.

In addition to presenting a concept design for the entire street, we presented two options at both the western Old South Head Road end, and the eastern Campbell Parade end, for the community's consideration. The recommended options at the western and eastern end were based on what the community has told us in the past, as documented in the Our Liveable Places Centres Strategy.

View the concept design options at the western and eastern ends.

Western end - Old South Head Rd intersection

A new shared path will connect Old South Head Rd to the new shared path and bike path on Curlewis St. Both options include a new raised pedestrian crossing at Simpson St, and continuation of the shared path east along Curlewis St. View the concept design options here.

Option 1: recommended design

This design removes the existing left turn slip lane from Old South Head Rd into Curlewis St, with the left turn movement still permitted, but controlled by the traffic signals. This creates additional public space at the corner which can be used for a wider shared path, additional parking and a raingarden.

Option 2: alternative design

This design retains the existing slip lane, allowing for a narrower shared path and smaller new turfing and landscaped areas. Pedestrians will still need to cross onto the traffic refuge in order to cross the street.

Eastern end - Campbell Pde intersection

A new separated two-way bike path will connect Curlewis St with Campbell Pde. Both options include new pedestrian crossings on Curlewis St west of Gould St, and on Gould St on the northern side of Curlewis St. View the concept design options here.

Option 1: recommended design

This design keeps the new bike path on the northern side of Curlewis St, crossing the pedestrian crossing near Gould St for a short distance at right angles.

Option 2: alternative design

This design sees the new bike path cross Curlewis St at the raised pedestrian crossing near Gould St. The bike path then continues towards Campbell Pde on the southern side of Curlewis St.

How feedback was collected

Feedback was collected via the following methods:

  • An online survey
  • Email: majorprojects@waverley.nsw.gov.au(External link)
  • Mail: c/o General Manager, PO Box 9, Bondi Junction NSW 1355
  • An online information session on Thursday, 2 June 2022, 6-7pm
  • An online information session for business owners on Monday, 6 June 2022, 4-5pm

Consultation: Second round

In May/June 2022 we asked for feedback on a draft concept design for this upgrade. The design at the western end of Curlewis Street was then updated at the western end of Curlewis Street (at the intersections with Old South Head Road and Simpson Street) to address feedback received during the initial consultation with regards to connectivity of the bike path and traffic flow.

From 21 November - 16 December 2022 we collected feedback on the updated design. Take a look at the key changes of the updated design, or review the updated concept design. All other aspects of the proposed upgrade were consulted on earlier this year.

How is the updated design different?

The updated design at the western end of Curlewis Street:

  • Removes the left hand turn into Simpson St (vehicles will still be able to turn left out of Simpson St)
  • Improves connectivity of the shared path as bikes and pedestrians will have a more direct route along Curlewis St
  • Allows room for two lanes of traffic travelling east from Old South Head Rd (one lane will continue onto Blair St and the other will continue onto Curlewis St)

There will be no net loss of parking on Simpson Street and no other vehicular movements will be impacted.

Map of updated design

Click image to view in full screen.

Map showing key features of the updated design at the western end of Curlewis Street

How feedback was collected

Feedback closed at 11.59pm, Friday 16 December 2022.

Existing layout vs updated design

Drag the slider left to right to compare the existing layout to the proposed layout described above.

Existing layout: Existing layout of Curlewis Street and Simpson Street intersection Proposed layout: Proposed changes to Curlewis street and Simpson Street intersection